Leads and Lags
A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. A lag is the amount of time a successor activity must be delayed with respect to a predecessor activity.
Know it well enough for the exam? Questions on Leads and Lags are scenario-based, not definitional.
Practice it freeExplanation
Leads and lags are used to fine-tune the logical relationships between activities in a project schedule network diagram. They modify the standard dependency relationships (FS, SS, FF, SF) by either accelerating or delaying the successor activity relative to the predecessor.
A lead allows activities to overlap. For example, in a Finish-to-Start relationship with a 5-day lead, the successor activity can start 5 days before the predecessor finishes. This is sometimes called negative lag. Leads are often used to compress the schedule by allowing concurrent work where possible. However, leads introduce risk because the successor begins before the predecessor is fully complete.
A lag introduces a mandatory waiting period between activities. For example, after pouring concrete (predecessor), there might be a 3-day lag before the next construction phase (successor) can begin because the concrete needs time to cure. Lags represent real waiting time and cannot be shortened without changing the nature of the work. Both leads and lags are defined during the Sequence Activities process and are critical to accurate schedule modeling.
Key Points
- •Lead: accelerates (overlaps) the successor activity
- •Lag: delays the successor activity by a mandatory waiting period
- •Applied to any of the four dependency types (FS, SS, FF, SF)
- •Leads compress the schedule but add risk; lags represent real wait times
Exam Tip
A lead is sometimes called "negative lag." On the exam, if you see a negative value for lag, it means a lead. Leads compress the schedule; lags extend it.
Frequently Asked Questions
Related Topics
Sequence Activities
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Precedence Diagramming Method (PDM)
The Precedence Diagramming Method (PDM) is a technique used to construct a schedule model in which activities are represented by nodes and are graphically linked by logical relationships to show the sequence of activities.
Finish-to-Start (FS) Dependency
A Finish-to-Start (FS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Schedule Compression
Schedule compression is a technique used to shorten or accelerate the project schedule duration without reducing the project scope.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Leads and Lags
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.