Skip to content
PMPCAPM

Leads and Lags

A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. A lag is the amount of time a successor activity must be delayed with respect to a predecessor activity.

Share:

Explanation

Leads and lags are used to fine-tune the logical relationships between activities in a project schedule network diagram. They modify the standard dependency relationships (FS, SS, FF, SF) by either accelerating or delaying the successor activity relative to the predecessor.

A lead allows activities to overlap. For example, in a Finish-to-Start relationship with a 5-day lead, the successor activity can start 5 days before the predecessor finishes. This is sometimes called negative lag. Leads are often used to compress the schedule by allowing concurrent work where possible. However, leads introduce risk because the successor begins before the predecessor is fully complete.

A lag introduces a mandatory waiting period between activities. For example, after pouring concrete (predecessor), there might be a 3-day lag before the next construction phase (successor) can begin because the concrete needs time to cure. Lags represent real waiting time and cannot be shortened without changing the nature of the work. Both leads and lags are defined during the Sequence Activities process and are critical to accurate schedule modeling.

Key Points

  • Lead: accelerates (overlaps) the successor activity
  • Lag: delays the successor activity by a mandatory waiting period
  • Applied to any of the four dependency types (FS, SS, FF, SF)
  • Leads compress the schedule but add risk; lags represent real wait times

Exam Tip

A lead is sometimes called "negative lag." On the exam, if you see a negative value for lag, it means a lead. Leads compress the schedule; lags extend it.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Schedule Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.