Skip to content
PMPCAPM

Schedule Compression

Schedule compression is a technique used to shorten or accelerate the project schedule duration without reducing the project scope.

Share:

Know it well enough for the exam? Questions on Schedule Compression are scenario-based, not definitional.

Practice it free

Explanation

Schedule compression techniques are applied when the project schedule needs to be shortened to meet a required deadline or to recover from schedule slippage. The key constraint is that the project scope cannot be reduced. The two primary schedule compression techniques are crashing and fast tracking.

Crashing involves adding resources to critical path activities to reduce their duration. This typically increases project cost because additional resources (overtime, additional staff, expedited materials) must be funded. Crashing is most effective when applied to critical path activities where additional resources can actually reduce the duration, and it is most efficient when the cost increase is minimal relative to the time saved.

Fast tracking involves performing activities in parallel that would normally be done sequentially. This is accomplished by overlapping activities or removing discretionary dependencies. Fast tracking does not necessarily increase cost, but it increases risk because activities are being performed concurrently with incomplete information from predecessors. Both techniques are applied to critical path activities because shortening non-critical path activities will not reduce the project duration.

Key Points

  • •Shortens the schedule without reducing scope
  • •Two main techniques: crashing and fast tracking
  • •Crashing adds resources (increases cost)
  • •Fast tracking overlaps activities (increases risk)

Exam Tip

Remember: crashing adds cost, fast tracking adds risk. Both must target the critical path. Compressing non-critical activities does not shorten the project.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Schedule Compression

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.