Skip to content
PMPCAPM

Schedule Compression

Schedule compression is a technique used to shorten or accelerate the project schedule duration without reducing the project scope.

Share:

Explanation

Schedule compression techniques are applied when the project schedule needs to be shortened to meet a required deadline or to recover from schedule slippage. The key constraint is that the project scope cannot be reduced. The two primary schedule compression techniques are crashing and fast tracking.

Crashing involves adding resources to critical path activities to reduce their duration. This typically increases project cost because additional resources (overtime, additional staff, expedited materials) must be funded. Crashing is most effective when applied to critical path activities where additional resources can actually reduce the duration, and it is most efficient when the cost increase is minimal relative to the time saved.

Fast tracking involves performing activities in parallel that would normally be done sequentially. This is accomplished by overlapping activities or removing discretionary dependencies. Fast tracking does not necessarily increase cost, but it increases risk because activities are being performed concurrently with incomplete information from predecessors. Both techniques are applied to critical path activities because shortening non-critical path activities will not reduce the project duration.

Key Points

  • Shortens the schedule without reducing scope
  • Two main techniques: crashing and fast tracking
  • Crashing adds resources (increases cost)
  • Fast tracking overlaps activities (increases risk)

Exam Tip

Remember: crashing adds cost, fast tracking adds risk. Both must target the critical path. Compressing non-critical activities does not shorten the project.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Schedule Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.