Skip to content
PMPCAPM

Finish-to-Start (FS) Dependency

A Finish-to-Start (FS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has finished.

Share:

Know it well enough for the exam? Questions on Finish-to-Start (FS) Dependency are scenario-based, not definitional.

Practice it free

Explanation

Finish-to-Start is the most common and intuitive dependency type in project scheduling. It represents the natural sequence where one activity must be completed before the next can begin. For example, the foundation of a building must be poured (predecessor finishes) before the framing can begin (successor starts).

FS dependencies account for the vast majority of relationships in most project schedule network diagrams. When no specific relationship type is stated, FS is the default assumption in project management tools and on the PMP and CAPM exams. The critical path method relies heavily on FS relationships to calculate early start, early finish, late start, and late finish dates.

Leads and lags can be applied to FS relationships to adjust timing. A lead on an FS relationship allows the successor to start before the predecessor fully finishes (overlapping work). A lag introduces a waiting period after the predecessor finishes before the successor can start. For example, concrete must cure (lag) after pouring before the next construction phase begins.

Key Points

  • •Most common dependency type in project scheduling
  • •Successor cannot start until predecessor finishes
  • •Default relationship type when none is specified
  • •Can be modified with leads (overlap) or lags (waiting period)

Exam Tip

FS is the default relationship. If an exam question describes a dependency without specifying the type, assume it is Finish-to-Start.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Finish-to-Start (FS) Dependency

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.