Finish-to-Start (FS) Dependency
A Finish-to-Start (FS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Explanation
Finish-to-Start is the most common and intuitive dependency type in project scheduling. It represents the natural sequence where one activity must be completed before the next can begin. For example, the foundation of a building must be poured (predecessor finishes) before the framing can begin (successor starts).
FS dependencies account for the vast majority of relationships in most project schedule network diagrams. When no specific relationship type is stated, FS is the default assumption in project management tools and on the PMP and CAPM exams. The critical path method relies heavily on FS relationships to calculate early start, early finish, late start, and late finish dates.
Leads and lags can be applied to FS relationships to adjust timing. A lead on an FS relationship allows the successor to start before the predecessor fully finishes (overlapping work). A lag introduces a waiting period after the predecessor finishes before the successor can start. For example, concrete must cure (lag) after pouring before the next construction phase begins.
Key Points
- •Most common dependency type in project scheduling
- •Successor cannot start until predecessor finishes
- •Default relationship type when none is specified
- •Can be modified with leads (overlap) or lags (waiting period)
Exam Tip
FS is the default relationship. If an exam question describes a dependency without specifying the type, assume it is Finish-to-Start.
Frequently Asked Questions
Related Topics
Precedence Diagramming Method (PDM)
The Precedence Diagramming Method (PDM) is a technique used to construct a schedule model in which activities are represented by nodes and are graphically linked by logical relationships to show the sequence of activities.
Start-to-Start (SS) Dependency
A Start-to-Start (SS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has started.
Finish-to-Finish (FF) Dependency
A Finish-to-Finish (FF) dependency is a logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Leads and Lags
A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. A lag is the amount of time a successor activity must be delayed with respect to a predecessor activity.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Relative Estimation
Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Part of
Schedule Management
Test your knowledge
Practice scenario-based questions on this topic with detailed explanations.