Skip to content
PMPCAPM

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Share:

Explanation

Earned Value Management compares the amount of work that was planned with what was actually accomplished and the actual cost incurred. It requires three key data points: Planned Value (PV), Earned Value (EV), and Actual Cost (AC). From these three measurements, variances and performance indices are calculated.

EVM enables the project manager to answer critical questions: Are we ahead of or behind schedule? Are we over or under budget? How much will the project cost at completion? By comparing EV to PV, schedule performance is measured. By comparing EV to AC, cost performance is measured.

Key EVM metrics include Schedule Variance (SV = EV - PV), Cost Variance (CV = EV - AC), Schedule Performance Index (SPI = EV / PV), Cost Performance Index (CPI = EV / AC), Estimate at Completion (EAC), Estimate to Complete (ETC), Variance at Completion (VAC), and To-Complete Performance Index (TCPI). EVM provides early warning signals of performance problems and supports data-driven decision making.

Key Points

  • Integrates scope, schedule, and cost measurement
  • Three foundational values: PV, EV, and AC
  • Calculates variances (SV, CV) and indices (SPI, CPI)
  • Enables forecasting of final project cost and schedule

Exam Tip

EVM is heavily tested on both PMP and CAPM exams. Memorize all formulas and know how to interpret positive/negative variances and indices above/below 1.0.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Predictive Life Cycle (Waterfall)

A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.