Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Know it well enough for the exam? Questions on Schedule Performance Index (SPI) are scenario-based, not definitional.
Practice it freeExplanation
The Schedule Performance Index measures how efficiently the project team is using its time. An SPI of 1.0 means the project is exactly on schedule. An SPI greater than 1.0 means the project is ahead of schedule, and an SPI less than 1.0 means the project is behind schedule.
The formula is SPI = EV / PV. For example, if EV = $40,000 and PV = $50,000, then SPI = 0.80, meaning the project is only accomplishing 80% of the planned work per unit of time. The project is progressing at 80% of its planned rate.
Like SV, SPI converges to 1.0 at project completion because all planned value will have been earned. SPI is used throughout the project to track schedule trends and is also used in some EAC formulas to forecast final project costs when schedule performance affects cost outcomes.
Key Points
- •Formula: SPI = EV / PV
- •SPI > 1.0 = ahead of schedule; SPI < 1.0 = behind schedule
- •Converges to 1.0 at project completion
- •Used in some EAC forecasting formulas
Exam Tip
SPI = EV / PV. Greater than 1.0 is good. An SPI of 0.8 means you are accomplishing only 80 cents of work for every dollar of planned work at this point.
Frequently Asked Questions
Related Topics
Planned Value (PV)
Planned Value (PV) is the authorized budget assigned to scheduled work, representing the value of work planned to be completed by a given point in time.
Earned Value (EV)
Earned Value (EV) is the measure of work performed expressed in terms of the budget authorized for that work.
Schedule Variance (SV)
Schedule Variance (SV) is an EVM metric that measures schedule performance as the difference between earned value and planned value: SV = EV - PV.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Cost Management
Practice Schedule Performance Index (SPI)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.