Skip to content
PMPCAPM

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Share:

Know it well enough for the exam? Questions on Resource Smoothing are scenario-based, not definitional.

Practice it free

Explanation

Resource smoothing is a gentler form of resource optimization compared to resource leveling. While both techniques aim to optimize resource usage, resource smoothing works within the constraint that the project end date and critical path cannot change. Adjustments are made only to non-critical activities that have available float.

The goal of resource smoothing is to reduce peaks and valleys in resource demand, creating a more even distribution of resource usage over time. For example, if a project has periods where five developers are needed followed by periods where only one is needed, resource smoothing would shift non-critical activities within their float windows to create a more balanced workload across all time periods.

Because resource smoothing only uses available float, it may not fully resolve all resource over-allocations. If the over-allocation involves critical path activities or activities without sufficient float, resource smoothing cannot help, and the project manager must use resource leveling (which may extend the schedule) or other strategies such as acquiring additional resources. Resource smoothing is preferred when maintaining the project end date is a higher priority than perfectly balanced resource usage.

Key Points

  • •Adjusts activities within their float to even out resource usage
  • •Does not change the project end date or critical path
  • •Less aggressive than resource leveling
  • •May not resolve all resource over-allocations

Exam Tip

The key distinction: resource leveling may extend the schedule; resource smoothing will not. Smoothing only uses available float and preserves the critical path.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Schedule Management

Study full domain →

Practice Resource Smoothing

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.