Sequence Activities
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Know it well enough for the exam? Questions on Sequence Activities are scenario-based, not definitional.
Practice it freeExplanation
Sequence Activities establishes the logical order in which project activities must be performed. The output of this process is the project schedule network diagram, which visually represents the dependencies between activities. This process turns a flat activity list into a logically connected network that can be analyzed for schedule optimization.
The primary tool used in this process is the Precedence Diagramming Method (PDM), which uses nodes to represent activities and arrows to show dependencies. Four types of logical relationships can exist: finish-to-start (FS), start-to-start (SS), finish-to-finish (FF), and start-to-finish (SF). Additionally, leads and lags can be applied to refine the timing of relationships.
Dependencies are classified as mandatory, discretionary, external, or internal. Mandatory dependencies are inherent to the nature of the work. Discretionary dependencies are established by the team based on best practices or preferences. External dependencies involve relationships with non-project activities. Internal dependencies are within the project team's control. Understanding these dependency types is critical for schedule optimization and risk analysis.
Key Points
- •Establishes logical relationships among project activities
- •Uses the Precedence Diagramming Method (PDM) as the primary technique
- •Produces the project schedule network diagram
- •Dependencies are classified as mandatory, discretionary, external, or internal
Exam Tip
Sequence Activities is about logical relationships, not durations. Duration estimates come in the next process (Estimate Activity Durations).
Frequently Asked Questions
Related Topics
Precedence Diagramming Method (PDM)
The Precedence Diagramming Method (PDM) is a technique used to construct a schedule model in which activities are represented by nodes and are graphically linked by logical relationships to show the sequence of activities.
Leads and Lags
A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. A lag is the amount of time a successor activity must be delayed with respect to a predecessor activity.
Mandatory Dependencies
Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work, often involving physical limitations.
Discretionary Dependencies
Discretionary dependencies are established by the project team based on knowledge of best practices, preferred sequencing, or past experience, even though other sequences are possible.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Sequence Activities
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.