Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Know it well enough for the exam? Questions on Cost Performance Index (CPI) are scenario-based, not definitional.
Practice it freeExplanation
The Cost Performance Index measures how efficiently the project is using its budget. A CPI of 1.0 means the project is exactly on budget. A CPI greater than 1.0 means the project is under budget (getting more value per dollar spent), and a CPI less than 1.0 means the project is over budget (getting less value per dollar spent).
The formula is CPI = EV / AC. For example, if EV = $40,000 and AC = $50,000, then CPI = 0.80, meaning the project is getting only 80 cents of value for every dollar spent.
CPI is considered the most critical EVM metric because research has shown that once a project reaches approximately 20% completion, CPI tends to remain relatively stable for the remainder of the project. This makes CPI a reliable predictor of final cost performance. CPI is also the most commonly used EAC forecasting factor.
Key Points
- •Formula: CPI = EV / AC
- •CPI > 1.0 = under budget; CPI < 1.0 = over budget
- •Most critical EVM metric; tends to stabilize after 20% completion
- •Primary input for EAC forecasting formulas
Exam Tip
CPI = EV / AC. Greater than 1.0 is good. CPI is the most important EVM metric and the most commonly tested. Once established, CPI rarely improves significantly.
Frequently Asked Questions
Related Topics
Earned Value (EV)
Earned Value (EV) is the measure of work performed expressed in terms of the budget authorized for that work.
Actual Cost (AC)
Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.
Cost Variance (CV)
Cost Variance (CV) is an EVM metric that measures cost performance as the difference between earned value and actual cost: CV = EV - AC.
Estimate at Completion (EAC)
Estimate at Completion (EAC) is the expected total cost of completing all work, calculated by projecting current performance into the future.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Cost Management
Practice Cost Performance Index (CPI)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.