Skip to content
PMPCAPM

Precedence Diagramming Method (PDM)

The Precedence Diagramming Method (PDM) is a technique used to construct a schedule model in which activities are represented by nodes and are graphically linked by logical relationships to show the sequence of activities.

Share:

Know it well enough for the exam? Questions on Precedence Diagramming Method (PDM) are scenario-based, not definitional.

Practice it free

Explanation

PDM, also known as Activity-on-Node (AON), is the standard method used in modern project management to create schedule network diagrams. In PDM, each activity is represented as a box (node) and arrows between boxes show the dependencies. This is different from the older Activity-on-Arrow (AOA) method, which is rarely used today.

PDM supports four types of logical relationships between activities: Finish-to-Start (FS), where the successor cannot start until the predecessor finishes; Start-to-Start (SS), where the successor cannot start until the predecessor starts; Finish-to-Finish (FF), where the successor cannot finish until the predecessor finishes; and Start-to-Finish (SF), where the successor cannot finish until the predecessor starts. Finish-to-Start is by far the most commonly used relationship type.

PDM also accommodates leads (acceleration of the successor) and lags (delay of the successor) to more precisely model the timing between dependent activities. The resulting network diagram is the foundation for critical path analysis and schedule development.

Key Points

  • •Also known as Activity-on-Node (AON)
  • •Activities are represented as nodes (boxes) with arrows showing dependencies
  • •Supports four relationship types: FS, SS, FF, and SF
  • •Foundation for critical path analysis and schedule modeling

Exam Tip

Finish-to-Start (FS) is the most commonly used and default dependency type in PDM. If no relationship type is specified on the exam, assume FS.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Precedence Diagramming Method (PDM)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.