Precedence Diagramming Method (PDM)
The Precedence Diagramming Method (PDM) is a technique used to construct a schedule model in which activities are represented by nodes and are graphically linked by logical relationships to show the sequence of activities.
Explanation
PDM, also known as Activity-on-Node (AON), is the standard method used in modern project management to create schedule network diagrams. In PDM, each activity is represented as a box (node) and arrows between boxes show the dependencies. This is different from the older Activity-on-Arrow (AOA) method, which is rarely used today.
PDM supports four types of logical relationships between activities: Finish-to-Start (FS), where the successor cannot start until the predecessor finishes; Start-to-Start (SS), where the successor cannot start until the predecessor starts; Finish-to-Finish (FF), where the successor cannot finish until the predecessor finishes; and Start-to-Finish (SF), where the successor cannot finish until the predecessor starts. Finish-to-Start is by far the most commonly used relationship type.
PDM also accommodates leads (acceleration of the successor) and lags (delay of the successor) to more precisely model the timing between dependent activities. The resulting network diagram is the foundation for critical path analysis and schedule development.
Key Points
- •Also known as Activity-on-Node (AON)
- •Activities are represented as nodes (boxes) with arrows showing dependencies
- •Supports four relationship types: FS, SS, FF, and SF
- •Foundation for critical path analysis and schedule modeling
Exam Tip
Finish-to-Start (FS) is the most commonly used and default dependency type in PDM. If no relationship type is specified on the exam, assume FS.
Frequently Asked Questions
Related Topics
Sequence Activities
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Finish-to-Start (FS) Dependency
A Finish-to-Start (FS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Start-to-Start (SS) Dependency
A Start-to-Start (SS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has started.
Finish-to-Finish (FF) Dependency
A Finish-to-Finish (FF) dependency is a logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Start-to-Finish (SF) Dependency
A Start-to-Finish (SF) dependency is a logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Relative Estimation
Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Part of
Schedule Management
Test your knowledge
Practice scenario-based questions on this topic with detailed explanations.