Discretionary Dependencies
Discretionary dependencies are established by the project team based on knowledge of best practices, preferred sequencing, or past experience, even though other sequences are possible.
Know it well enough for the exam? Questions on Discretionary Dependencies are scenario-based, not definitional.
Practice it freeExplanation
Discretionary dependencies, also called preferred logic, preferential logic, or soft logic, are relationships that the project team chooses to implement but that are not physically or contractually required. They reflect the team's judgment about the best order to perform activities based on experience, industry best practices, or organizational standards.
For example, a team might decide to complete all design work before beginning any development work, even though some development could theoretically start before all designs are finalized. This sequencing preference creates a discretionary dependency. While it may reduce risk or improve quality, it is not an inherent requirement of the work.
Discretionary dependencies are important in schedule optimization because they can be modified or removed during schedule compression. When fast tracking, the project team looks for discretionary dependencies that can be relaxed to allow activities to overlap. However, changing discretionary dependencies increases risk, so the team must carefully evaluate the tradeoffs. All discretionary dependencies should be documented so they can be reviewed later if schedule changes are needed.
Key Points
- •Also called soft logic, preferred logic, or preferential logic
- •Based on best practices, experience, or team preference
- •Can be modified or removed for schedule compression
- •Should be fully documented for future review
Exam Tip
Discretionary dependencies are the ones you can change when fast tracking. They are based on preference, not physical or contractual necessity.
Frequently Asked Questions
Related Topics
Mandatory Dependencies
Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work, often involving physical limitations.
Fast Tracking
Fast tracking is a schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Sequence Activities
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Schedule Compression
Schedule compression is a technique used to shorten or accelerate the project schedule duration without reducing the project scope.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Discretionary Dependencies
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.