Mandatory Dependencies
Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work, often involving physical limitations.
Know it well enough for the exam? Questions on Mandatory Dependencies are scenario-based, not definitional.
Practice it freeExplanation
Mandatory dependencies, also called hard logic or hard dependencies, represent relationships that cannot be changed by the project team. They arise from the physical or contractual nature of the work being performed. For example, in construction, a foundation must be laid before walls can be erected. This is a physical constraint that cannot be altered regardless of project preferences.
Mandatory dependencies are identified during the Sequence Activities process and are distinguished from discretionary dependencies, which the team can choose to modify. Recognizing whether a dependency is mandatory or discretionary is critical for schedule optimization. When the team needs to compress the schedule through fast tracking, only discretionary dependencies can be relaxed. Mandatory dependencies must be respected.
Mandatory dependencies can be internal (within the project) or external (involving outside entities). For example, a contractual requirement to deliver a component by a certain date before the next phase can begin is a mandatory external dependency. Understanding the nature of each dependency helps the project team make informed decisions about schedule changes and risk.
Key Points
- •Also called hard logic or hard dependencies
- •Cannot be changed by the project team
- •Arise from physical limitations, legal requirements, or contractual obligations
- •Must be respected during schedule compression efforts
Exam Tip
When fast tracking, only discretionary dependencies can be adjusted. Mandatory dependencies are fixed and cannot be changed regardless of schedule pressure.
Frequently Asked Questions
Related Topics
Discretionary Dependencies
Discretionary dependencies are established by the project team based on knowledge of best practices, preferred sequencing, or past experience, even though other sequences are possible.
External Dependencies
External dependencies involve a relationship between project activities and non-project activities that are outside the project team's control.
Internal Dependencies
Internal dependencies involve a relationship between project activities that are within the project team's control.
Fast Tracking
Fast tracking is a schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Mandatory Dependencies
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.