Skip to content
PMPCAPM

Fast Tracking

Fast tracking is a schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

Share:

Know it well enough for the exam? Questions on Fast Tracking are scenario-based, not definitional.

Practice it free

Explanation

Fast tracking accelerates the project schedule by overlapping activities that were originally planned to be performed sequentially. This is achieved by modifying discretionary dependencies to allow parallel execution or by starting successor activities before predecessors are fully complete. Fast tracking does not require additional resources, so it does not directly increase project cost.

Fast tracking is only effective when applied to activities on the critical path that can logically overlap. For example, if a project plan shows design followed by development in a strict sequence, fast tracking might allow development to begin on completed portions of the design while other design work continues. This requires that the activities be divisible and that partial outputs from the predecessor can feed the successor.

The primary drawback of fast tracking is increased risk. When activities overlap, the successor begins with incomplete information from the predecessor. If the predecessor's output changes after the successor has started, rework may be required. Fast tracking also increases complexity because the team must manage concurrent work streams with interdependencies. Only discretionary dependencies can be fast tracked; mandatory dependencies cannot be changed.

Key Points

  • •Performs sequential activities in parallel to compress the schedule
  • •Does not directly increase cost but increases risk
  • •Only works with discretionary dependencies on the critical path
  • •May result in rework if predecessor outputs change after successor starts

Exam Tip

Fast tracking increases risk (especially rework risk) but not necessarily cost. Crashing increases cost. Know which is which for the exam.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Fast Tracking

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.