Withdrawing/Avoiding
Withdrawing (also called avoiding) is a conflict resolution technique where one or both parties retreat from the conflict, postponing the issue or declining to engage.
Know it well enough for the exam? Questions on Withdrawing/Avoiding are scenario-based, not definitional.
Practice it freeExplanation
Withdrawing means stepping away from the conflict rather than addressing it. This technique neither resolves the conflict nor satisfies any party. The issue is simply deferred or ignored. PMI generally considers this the least desirable conflict resolution technique because it leaves the problem unresolved.\n\nHowever, withdrawing can be strategically appropriate in certain situations: when the issue is trivial, when emotions are too high for productive discussion and a cooling-off period is needed, when you have no chance of satisfying your concerns, or when the potential damage from confrontation outweighs the benefits of resolving the issue now.\n\nThe primary risk of withdrawing is that unresolved conflicts tend to escalate over time. What starts as a minor disagreement can become a major issue if repeatedly avoided. Project managers should use this technique sparingly and ensure they return to address the conflict once conditions are more favorable.
Key Points
- •One or both parties retreat from the conflict
- •Issue is postponed, deferred, or ignored
- •Generally the least desirable technique per PMI
- •Can be appropriate as a temporary measure when emotions are high
Exam Tip
Withdrawing is the worst long-term strategy because nothing is resolved. However, it may be correct when a cooling-off period is needed or when the issue is genuinely trivial.
Frequently Asked Questions
Related Topics
Conflict Management
Conflict management is the practice of identifying and handling conflicts in a timely, constructive manner to minimize negative impacts and leverage disagreement for improved outcomes.
Smoothing/Accommodating
Smoothing (also called accommodating) is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference, often at the expense of one party who yields to maintain harmony.
Forcing/Directing
Forcing (also called directing) is a conflict resolution technique where one party pushes their viewpoint at the expense of others, typically using positional power to resolve the disagreement.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Resource Management
Practice Withdrawing/Avoiding
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.