Smoothing/Accommodating
Smoothing (also called accommodating) is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference, often at the expense of one party who yields to maintain harmony.
Know it well enough for the exam? Questions on Smoothing/Accommodating are scenario-based, not definitional.
Practice it freeExplanation
Smoothing focuses on de-escalating the conflict by highlighting common ground and minimizing the perceived differences between parties. The person using this technique may downplay the importance of the disagreement or yield their position to maintain relationships and team harmony.\n\nThis approach is useful when the issue is more important to the other party, when preserving the relationship is the top priority, when the person realizes they are wrong, or when continued conflict would be more damaging than conceding. It provides a temporary resolution and can keep the team functioning while a more permanent solution is developed.\n\nThe main drawback is that smoothing does not resolve the underlying conflict. The issue is suppressed rather than addressed, which means it may resurface later in a more intense form. PMI considers this a lose-win approach because one party sacrifices their needs to satisfy the other.
Key Points
- •Emphasizes areas of agreement over areas of difference
- •One party yields to maintain harmony (lose-win)
- •Provides temporary relief but does not resolve root causes
- •Useful when the relationship is more important than the issue
Exam Tip
Smoothing focuses on what the parties agree on, not what they disagree on. It is a temporary fix. If a scenario describes someone downplaying differences to keep peace, that is smoothing.
Frequently Asked Questions
Related Topics
Conflict Management
Conflict management is the practice of identifying and handling conflicts in a timely, constructive manner to minimize negative impacts and leverage disagreement for improved outcomes.
Compromising
Compromising (also called reconciling) is a conflict resolution technique where each party gives up something to reach a mutually acceptable solution, resulting in a lose-lose outcome.
Withdrawing/Avoiding
Withdrawing (also called avoiding) is a conflict resolution technique where one or both parties retreat from the conflict, postponing the issue or declining to engage.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Resource Management
Practice Smoothing/Accommodating
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.