Skip to content
PMPCAPM

Forcing/Directing

Forcing (also called directing) is a conflict resolution technique where one party pushes their viewpoint at the expense of others, typically using positional power to resolve the disagreement.

Share:

Explanation

Forcing involves one person imposing their solution on the other parties. This is a win-lose approach where the person with more power or authority prevails. It is the most aggressive conflict resolution technique and is generally not recommended by PMI as a default approach.\n\nHowever, forcing can be appropriate in specific situations: when a quick decision is needed and there is no time for discussion, when the issue involves safety or compliance where there is only one correct answer, when an unpopular but necessary action must be taken, or when the decision-maker is confident they are right and the cost of delay outweighs the cost of overriding others.\n\nThe significant drawback of forcing is that it damages relationships, reduces team morale, and discourages future collaboration. Team members who are overruled may become disengaged, resist implementation, or harbor resentment. Forcing should be used sparingly and only when the situation genuinely requires it.

Key Points

  • One party imposes their solution using authority or power (win-lose)
  • Appropriate for emergencies, safety issues, or time-critical decisions
  • Damages relationships and reduces team morale
  • Generally not recommended as a default conflict resolution approach

Exam Tip

Forcing is win-lose and is generally not preferred by PMI. However, it may be the correct answer when the scenario involves an emergency, safety risk, or non-negotiable requirement.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Resource Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.