Skip to content
PMPCAPM

Schedule Variance (SV)

Schedule Variance (SV) is an EVM metric that measures schedule performance as the difference between earned value and planned value: SV = EV - PV.

Share:

Explanation

Schedule Variance indicates whether the project is ahead of or behind the planned schedule in monetary terms. A positive SV means the project has earned more value than was planned by a given date, indicating the project is ahead of schedule. A negative SV means less value has been earned than planned, indicating the project is behind schedule. An SV of zero means the project is exactly on schedule.

The formula is SV = EV - PV. For example, if EV = $45,000 and PV = $50,000, then SV = -$5,000, meaning the project is behind schedule by $5,000 worth of work.

At project completion, SV will always equal zero because all planned value will have been earned. This is a known limitation of SV as a schedule measure, as it cannot detect schedule delays once the project is complete. For this reason, SV is most useful during project execution for early detection of schedule deviations.

Key Points

  • Formula: SV = EV - PV
  • Positive SV = ahead of schedule; negative SV = behind schedule
  • SV equals zero at project completion regardless of actual delays
  • Expressed in monetary units, not time units

Exam Tip

SV = EV - PV. Positive is good (ahead of schedule). Remember that SV always goes to zero at project end, which is a limitation of this metric.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.