Planned Value (PV)
Planned Value (PV) is the authorized budget assigned to scheduled work, representing the value of work planned to be completed by a given point in time.
Know it well enough for the exam? Questions on Planned Value (PV) are scenario-based, not definitional.
Practice it freeExplanation
Planned Value, formerly known as Budgeted Cost of Work Scheduled (BCWS), represents the approved budget allocated for the work scheduled to be completed by a specific date. It is the baseline against which earned value is compared to determine schedule performance.
PV is a cumulative value that increases over time as more work is scheduled. At the end of the project, the total PV equals the Budget at Completion (BAC), which is the total planned value for all work on the project. PV is always based on the approved cost baseline.
For example, if a project has a BAC of $100,000 and is planned to be 50% complete at the end of month 3, then the PV at month 3 is $50,000. PV is determined before the work is performed and represents what should have been accomplished according to the plan.
Key Points
- •Formerly known as Budgeted Cost of Work Scheduled (BCWS)
- •Represents the authorized budget for scheduled work at a point in time
- •Total PV at project end equals Budget at Completion (BAC)
- •Determined from the cost baseline before work is performed
Exam Tip
PV answers: What was the budget for the work that was supposed to be done by now? Total PV at project completion equals BAC.
Frequently Asked Questions
Related Topics
Earned Value (EV)
Earned Value (EV) is the measure of work performed expressed in terms of the budget authorized for that work.
Actual Cost (AC)
Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.
Schedule Variance (SV)
Schedule Variance (SV) is an EVM metric that measures schedule performance as the difference between earned value and planned value: SV = EV - PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Planned Value (PV)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.