Cost Variance (CV)
Cost Variance (CV) is an EVM metric that measures cost performance as the difference between earned value and actual cost: CV = EV - AC.
Know it well enough for the exam? Questions on Cost Variance (CV) are scenario-based, not definitional.
Practice it freeExplanation
Cost Variance indicates whether the project is over or under budget for the work completed. A positive CV means the project has spent less than budgeted for the work accomplished, indicating the project is under budget. A negative CV means the project has spent more than budgeted, indicating it is over budget. A CV of zero means the project is exactly on budget.
The formula is CV = EV - AC. For example, if EV = $45,000 and AC = $50,000, then CV = -$5,000, meaning the project is $5,000 over budget for the work completed.
Unlike SV, CV does not converge to zero at project completion. It remains a valid indicator of cumulative cost performance throughout the entire project and at project close. A negative CV at completion indicates the project finished over budget. CV is considered one of the most important EVM metrics because cost variances are typically difficult to recover from later in the project.
Key Points
- •Formula: CV = EV - AC
- •Positive CV = under budget; negative CV = over budget
- •Does not converge to zero at project completion (unlike SV)
- •Considered a critical indicator because cost overruns are hard to recover
Exam Tip
CV = EV - AC. Positive is good (under budget). Unlike SV, CV remains meaningful at project end. A negative CV at completion means the project finished over budget.
Frequently Asked Questions
Related Topics
Earned Value (EV)
Earned Value (EV) is the measure of work performed expressed in terms of the budget authorized for that work.
Actual Cost (AC)
Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Variance (SV)
Schedule Variance (SV) is an EVM metric that measures schedule performance as the difference between earned value and planned value: SV = EV - PV.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Cost Variance (CV)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.