Skip to content
PMPCAPM

Cost Variance (CV)

Cost Variance (CV) is an EVM metric that measures cost performance as the difference between earned value and actual cost: CV = EV - AC.

Share:

Explanation

Cost Variance indicates whether the project is over or under budget for the work completed. A positive CV means the project has spent less than budgeted for the work accomplished, indicating the project is under budget. A negative CV means the project has spent more than budgeted, indicating it is over budget. A CV of zero means the project is exactly on budget.

The formula is CV = EV - AC. For example, if EV = $45,000 and AC = $50,000, then CV = -$5,000, meaning the project is $5,000 over budget for the work completed.

Unlike SV, CV does not converge to zero at project completion. It remains a valid indicator of cumulative cost performance throughout the entire project and at project close. A negative CV at completion indicates the project finished over budget. CV is considered one of the most important EVM metrics because cost variances are typically difficult to recover from later in the project.

Key Points

  • Formula: CV = EV - AC
  • Positive CV = under budget; negative CV = over budget
  • Does not converge to zero at project completion (unlike SV)
  • Considered a critical indicator because cost overruns are hard to recover

Exam Tip

CV = EV - AC. Positive is good (under budget). Unlike SV, CV remains meaningful at project end. A negative CV at completion means the project finished over budget.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.