Earned Value (EV)
Earned Value (EV) is the measure of work performed expressed in terms of the budget authorized for that work.
Know it well enough for the exam? Questions on Earned Value (EV) are scenario-based, not definitional.
Practice it freeExplanation
Earned Value, formerly known as Budgeted Cost of Work Performed (BCWP), represents the value of work actually completed measured against the planned budget. It is the central metric in EVM because it is compared to both PV (for schedule performance) and AC (for cost performance).
EV is calculated by multiplying the percent complete of each activity by its planned budget. For example, if an activity was budgeted at $10,000 and is 60% complete, the EV is $6,000. EV can never exceed the BAC for the project.
EV must be measured consistently using the rules established in the cost management plan. Common measurement methods include the fixed formula (such as 0/100 or 50/50), weighted milestone, and percent complete. The method chosen should be appropriate for the type of work being measured.
Key Points
- •Formerly known as Budgeted Cost of Work Performed (BCWP)
- •Measures completed work in terms of its authorized budget
- •EV = percent complete multiplied by the budget for that work
- •Can never exceed the Budget at Completion (BAC)
Exam Tip
EV answers: What is the budgeted value of the work actually completed? It is always compared to PV for schedule analysis and to AC for cost analysis.
Frequently Asked Questions
Related Topics
Planned Value (PV)
Planned Value (PV) is the authorized budget assigned to scheduled work, representing the value of work planned to be completed by a given point in time.
Actual Cost (AC)
Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.
Cost Variance (CV)
Cost Variance (CV) is an EVM metric that measures cost performance as the difference between earned value and actual cost: CV = EV - AC.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Earned Value (EV)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.