Skip to content
PMPCAPM

Float (Total Float and Free Float)

Total float is the amount of time an activity can be delayed from its early start without delaying the project finish date. Free float is the amount of time an activity can be delayed without delaying the early start of any successor activity.

Share:

Know it well enough for the exam? Questions on Float (Total Float and Free Float) are scenario-based, not definitional.

Practice it free

Explanation

Float (also called slack) measures the scheduling flexibility available for an activity. Understanding float is essential for schedule management because it identifies which activities have room for delay and which are time-critical.

Total float is calculated as Late Start minus Early Start (LS - ES) or Late Finish minus Early Finish (LF - EF). It represents how long an activity can be delayed without affecting the project completion date. Activities on the critical path have zero total float. Activities with positive total float can be delayed by up to that amount without impacting the project end date, though they may affect the timing of non-critical paths.

Free float is the amount of time an activity can be delayed without affecting the early start of any immediately succeeding activity. Free float is always less than or equal to total float. An activity can have total float but zero free float if delaying it would push out a successor's early start (even though it would not delay the project). Project float (also called project slack) is the amount of time the project can be delayed without exceeding an externally imposed completion date.

Key Points

  • •Total float: delay allowed without affecting the project finish date (LS - ES or LF - EF)
  • •Free float: delay allowed without affecting any successor's early start
  • •Critical path activities have zero total float
  • •Free float is always less than or equal to total float

Exam Tip

Know the difference between total float and free float. Total float = LS - ES. Free float = ES of successor - EF of current activity. Both are commonly tested.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Float (Total Float and Free Float)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.