Skip to content
PMPCAPM

Float (Total Float and Free Float)

Total float is the amount of time an activity can be delayed from its early start without delaying the project finish date. Free float is the amount of time an activity can be delayed without delaying the early start of any successor activity.

Share:

Explanation

Float (also called slack) measures the scheduling flexibility available for an activity. Understanding float is essential for schedule management because it identifies which activities have room for delay and which are time-critical.

Total float is calculated as Late Start minus Early Start (LS - ES) or Late Finish minus Early Finish (LF - EF). It represents how long an activity can be delayed without affecting the project completion date. Activities on the critical path have zero total float. Activities with positive total float can be delayed by up to that amount without impacting the project end date, though they may affect the timing of non-critical paths.

Free float is the amount of time an activity can be delayed without affecting the early start of any immediately succeeding activity. Free float is always less than or equal to total float. An activity can have total float but zero free float if delaying it would push out a successor's early start (even though it would not delay the project). Project float (also called project slack) is the amount of time the project can be delayed without exceeding an externally imposed completion date.

Key Points

  • Total float: delay allowed without affecting the project finish date (LS - ES or LF - EF)
  • Free float: delay allowed without affecting any successor's early start
  • Critical path activities have zero total float
  • Free float is always less than or equal to total float

Exam Tip

Know the difference between total float and free float. Total float = LS - ES. Free float = ES of successor - EF of current activity. Both are commonly tested.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Schedule Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.