Skip to content
PMPCAPM

Develop Schedule

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution, monitoring, and controlling.

Share:

Know it well enough for the exam? Questions on Develop Schedule are scenario-based, not definitional.

Practice it free

Explanation

Develop Schedule integrates all the outputs from the preceding scheduling processes (Define Activities, Sequence Activities, Estimate Activity Durations, and Estimate Activity Resources) to build the project schedule model. This model determines planned start and finish dates for each activity and establishes the overall project timeline.

Key techniques used in this process include the Critical Path Method (CPM), resource optimization (leveling and smoothing), schedule compression (crashing and fast tracking), and what-if scenario analysis. The critical path method calculates the longest path through the network, determining the minimum project duration and identifying activities with zero float. Resource optimization adjusts the schedule to address resource constraints or smooth resource usage.

The outputs of Develop Schedule include the schedule baseline, the project schedule (commonly presented as a Gantt chart, milestone chart, or project schedule network diagram), schedule data, project calendars, and updates to the project management plan. The schedule baseline is the approved version of the schedule model and serves as the basis for measuring and reporting schedule performance throughout the project.

Key Points

  • •Integrates all scheduling inputs to create the schedule model
  • •Uses CPM, resource optimization, and schedule compression techniques
  • •Produces the schedule baseline and project schedule presentations
  • •Schedule model determines planned start and finish dates for all activities

Exam Tip

Develop Schedule is an iterative process. After initial development, resource constraints, risk responses, and changes may require the schedule to be recalculated multiple times.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Develop Schedule

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.