Critical Path

The critical path is the longest sequence of activities in a project schedule network diagram that determines the shortest possible project duration.

Share:

Know it well enough for the exam? Questions on Critical Path are scenario-based, not definitional.

Practice it free

Explanation

The critical path represents the sequence of dependent activities that takes the longest total time to complete. Every project has at least one critical path, and some projects have multiple critical paths of equal length. The length of the critical path defines the minimum possible duration of the project; the project cannot be completed any faster without compressing activities on this path.

Activities on the critical path have zero total float, meaning they have no scheduling flexibility. If any critical path activity is delayed by even one day, the entire project will be delayed by one day (assuming no other changes). This makes critical path activities the highest priority for schedule monitoring and control.

A project can have multiple critical paths, which increases schedule risk because a delay on any of the critical paths will delay the project. The critical path can also change during the project as activities are completed ahead of or behind schedule, or as changes are made to the project scope, resources, or constraints. The near-critical path (the path with the smallest amount of float that is not zero) should also be monitored closely, as it can become the critical path if delays occur.

Key Points

  • •Longest path through the network diagram
  • •Determines the minimum project duration
  • •Activities on the critical path have zero total float
  • •A project can have multiple critical paths, increasing risk

Exam Tip

The critical path is the LONGEST path, not the shortest. Multiple critical paths increase project risk. Always monitor near-critical paths as well.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →