External Dependencies
External dependencies involve a relationship between project activities and non-project activities that are outside the project team's control.
Know it well enough for the exam? Questions on External Dependencies are scenario-based, not definitional.
Practice it freeExplanation
External dependencies exist when project activities depend on factors outside the project team's authority or control. These dependencies typically involve third parties, regulatory bodies, vendors, or other projects within the organization. Because they are outside the team's direct control, external dependencies introduce additional uncertainty and risk into the schedule.
Examples of external dependencies include waiting for a government agency to issue a permit before construction can begin, depending on a vendor to deliver equipment before installation activities can start, or needing another project team to complete an interface before integration testing can proceed. These dependencies cannot be managed solely through internal project decisions.
External dependencies require proactive monitoring and communication with the external parties involved. The project manager should track the status of external dependencies closely and may need to build buffer time into the schedule to account for potential delays. External dependencies can be either mandatory (legally required permits) or discretionary (choosing to wait for a vendor recommendation rather than proceeding independently).
Key Points
- •Involve relationships with activities outside the project team's control
- •Include vendor deliveries, permits, regulatory approvals, and other project outputs
- •Introduce additional risk and uncertainty into the schedule
- •Require proactive monitoring and communication with external parties
Exam Tip
External dependencies are outside your control, so they carry higher schedule risk. Build buffers and monitor them closely.
Frequently Asked Questions
Related Topics
Internal Dependencies
Internal dependencies involve a relationship between project activities that are within the project team's control.
Mandatory Dependencies
Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work, often involving physical limitations.
Discretionary Dependencies
Discretionary dependencies are established by the project team based on knowledge of best practices, preferred sequencing, or past experience, even though other sequences are possible.
Sequence Activities
Sequence Activities is the process of identifying and documenting relationships among the project activities.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice External Dependencies
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.