Skip to content
PMPCAPM

Estimate at Completion (EAC)

Estimate at Completion (EAC) is the expected total cost of completing all work, calculated by projecting current performance into the future.

Share:

Explanation

EAC is a forecast of the most likely total cost of the project based on current performance data. There are four common formulas for calculating EAC, each used under different assumptions.

1. EAC = AC + (BAC - EV) / CPI — Used when current cost performance is expected to continue. This is the most commonly used formula. 2. EAC = AC + (BAC - EV) — Used when future work will be accomplished at the budgeted rate, regardless of past performance (atypical variance). 3. EAC = AC + Bottom-up ETC — Used when the original estimate is fundamentally flawed and a new estimate is needed for remaining work. 4. EAC = AC + (BAC - EV) / (CPI x SPI) — Used when both cost and schedule performance are expected to influence remaining work.

The choice of formula depends on the project manager's assessment of what factors will influence the remaining work. EAC is compared to BAC to determine whether the project will finish over or under the original budget. If EAC exceeds BAC, the project is projected to finish over budget.

Key Points

  • Most common formula: EAC = BAC / CPI (equivalent to AC + (BAC - EV) / CPI)
  • Atypical variance: EAC = AC + (BAC - EV)
  • New estimate: EAC = AC + Bottom-up ETC
  • Cost and schedule influence: EAC = AC + (BAC - EV) / (CPI x SPI)

Exam Tip

Know all four EAC formulas and when to use each. The most common is EAC = BAC / CPI. If the question says past variances were atypical, use EAC = AC + (BAC - EV).

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.