Skip to content
PMPCAPM

Estimate at Completion (EAC)

Estimate at Completion (EAC) is the expected total cost of completing all work, calculated by projecting current performance into the future.

Share:

Know it well enough for the exam? Questions on Estimate at Completion (EAC) are scenario-based, not definitional.

Practice it free

Explanation

EAC is a forecast of the most likely total cost of the project based on current performance data. There are four common formulas for calculating EAC, each used under different assumptions.

1. EAC = AC + (BAC - EV) / CPI — Used when current cost performance is expected to continue. This is the most commonly used formula. 2. EAC = AC + (BAC - EV) — Used when future work will be accomplished at the budgeted rate, regardless of past performance (atypical variance). 3. EAC = AC + Bottom-up ETC — Used when the original estimate is fundamentally flawed and a new estimate is needed for remaining work. 4. EAC = AC + (BAC - EV) / (CPI x SPI) — Used when both cost and schedule performance are expected to influence remaining work.

The choice of formula depends on the project manager's assessment of what factors will influence the remaining work. EAC is compared to BAC to determine whether the project will finish over or under the original budget. If EAC exceeds BAC, the project is projected to finish over budget.

Key Points

  • •Most common formula: EAC = BAC / CPI (equivalent to AC + (BAC - EV) / CPI)
  • •Atypical variance: EAC = AC + (BAC - EV)
  • •New estimate: EAC = AC + Bottom-up ETC
  • •Cost and schedule influence: EAC = AC + (BAC - EV) / (CPI x SPI)

Exam Tip

Know all four EAC formulas and when to use each. The most common is EAC = BAC / CPI. If the question says past variances were atypical, use EAC = AC + (BAC - EV).

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Estimate at Completion (EAC)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.