Estimate to Complete (ETC)
Estimate to Complete (ETC) is the expected cost needed to finish all remaining project work from the current point in time.
Know it well enough for the exam? Questions on Estimate to Complete (ETC) are scenario-based, not definitional.
Practice it freeExplanation
ETC represents the cost forecast for the work that has not yet been completed. It answers the question: How much more will it cost to finish the project? The relationship between EAC, AC, and ETC is: EAC = AC + ETC, which can be rearranged to ETC = EAC - AC.
When current performance is expected to continue, ETC is calculated as: ETC = (BAC - EV) / CPI. When past variances are considered atypical and future work is expected to proceed at the budgeted rate: ETC = BAC - EV. A third approach is to develop a completely new bottom-up estimate for the remaining work.
ETC is useful for determining how much additional funding may be needed and for making decisions about whether to continue, modify, or terminate the project. It should be reviewed periodically as project conditions change.
Key Points
- •ETC = EAC - AC (general relationship)
- •Typical variance: ETC = (BAC - EV) / CPI
- •Atypical variance: ETC = BAC - EV
- •Can also be a new bottom-up estimate for remaining work
Exam Tip
ETC answers: How much more will it cost? The most common calculation is ETC = EAC - AC. If you know CPI, use ETC = (BAC - EV) / CPI.
Frequently Asked Questions
Related Topics
Estimate at Completion (EAC)
Estimate at Completion (EAC) is the expected total cost of completing all work, calculated by projecting current performance into the future.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Variance at Completion (VAC)
Variance at Completion (VAC) is the projected difference between the budget at completion and the estimate at completion: VAC = BAC - EAC.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Estimate to Complete (ETC)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.