Skip to content
PMPCAPM

To-Complete Performance Index (TCPI)

The To-Complete Performance Index (TCPI) is a measure of the cost performance that must be achieved on remaining work to meet a specified management goal, either the BAC or EAC.

Share:

Know it well enough for the exam? Questions on To-Complete Performance Index (TCPI) are scenario-based, not definitional.

Practice it free

Explanation

TCPI calculates the required efficiency for the remaining work to achieve a cost target. There are two versions of the formula depending on the target.

To finish within the original budget: TCPI = (BAC - EV) / (BAC - AC). To finish within the revised estimate: TCPI = (BAC - EV) / (EAC - AC). The numerator in both formulas is the same: the remaining work expressed in budgeted terms (BAC - EV). The denominator represents the remaining funds available.

A TCPI greater than 1.0 means the team must perform more efficiently than planned to meet the target. A TCPI of exactly 1.0 means current efficiency is sufficient. A TCPI less than 1.0 means the team can afford to be less efficient and still meet the target. The higher the TCPI, the harder it becomes to achieve the goal, particularly values above 1.1 to 1.2, which are generally considered unrealistic to sustain.

Key Points

  • •Based on BAC: TCPI = (BAC - EV) / (BAC - AC)
  • •Based on EAC: TCPI = (BAC - EV) / (EAC - AC)
  • •TCPI > 1.0 = must improve efficiency; TCPI < 1.0 = can relax efficiency
  • •Values above 1.1-1.2 are generally considered very difficult to achieve

Exam Tip

Know both TCPI formulas. The BAC-based version asks: Can we still meet the original budget? The EAC-based version asks: Can we meet the revised forecast? TCPI > 1.0 means harder work ahead.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice To-Complete Performance Index (TCPI)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.