Skip to content
PMPCAPM

Variance at Completion (VAC)

Variance at Completion (VAC) is the projected difference between the budget at completion and the estimate at completion: VAC = BAC - EAC.

Share:

Know it well enough for the exam? Questions on Variance at Completion (VAC) are scenario-based, not definitional.

Practice it free

Explanation

VAC forecasts the expected budget surplus or deficit at the end of the project. A positive VAC indicates the project is projected to finish under budget, while a negative VAC indicates it will finish over budget. A VAC of zero means the project is expected to finish exactly on budget.

The formula is VAC = BAC - EAC. For example, if the BAC is $500,000 and the EAC is $550,000, then VAC = -$50,000, meaning the project is forecast to be $50,000 over budget at completion.

VAC provides a simple, quick assessment of overall project cost health. It is useful for reporting to stakeholders and for making decisions about whether corrective action is needed. VAC should be evaluated alongside CPI and other metrics for a complete picture of cost performance.

Key Points

  • •Formula: VAC = BAC - EAC
  • •Positive VAC = projected under budget; negative VAC = projected over budget
  • •Provides a quick summary of expected cost outcome
  • •Used for stakeholder reporting and corrective action decisions

Exam Tip

VAC = BAC - EAC. Positive is good (under budget at completion). This is a straightforward formula but be sure to calculate EAC correctly first.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Variance at Completion (VAC)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.