Determine Budget
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Know it well enough for the exam? Questions on Determine Budget are scenario-based, not definitional.
Practice it freeExplanation
Determine Budget takes the activity cost estimates and aggregates them into work package costs, then into control account costs, and finally into the total project cost baseline. The cost baseline is the approved version of the time-phased project budget, excluding management reserves.
Key inputs to this process include the cost management plan, scope baseline (project scope statement, WBS, and WBS dictionary), activity cost estimates, basis of estimates, project schedule, resource calendars, risk register, agreements, and organizational process assets.
The primary outputs are the cost baseline, project funding requirements, and project document updates. The cost baseline serves as the reference point for measuring and monitoring cost performance. The project budget equals the cost baseline plus management reserves.
Key Points
- •Aggregates cost estimates to establish the cost baseline
- •Cost baseline is the approved time-phased project budget
- •Project budget = cost baseline + management reserves
- •Funding requirements are also determined in this process
Exam Tip
Determine Budget produces the cost baseline and funding requirements. Remember the equation: Project Budget = Cost Baseline (includes contingency reserves) + Management Reserves.
Frequently Asked Questions
Related Topics
Cost Baseline
The cost baseline is the approved version of the time-phased project budget, excluding management reserves, used as a reference for measuring and monitoring cost performance.
Project Budget
The project budget is the total authorized funds allocated for the project, composed of the cost baseline plus management reserves.
Funding Requirements
Funding requirements define the total and periodic funding needs derived from the cost baseline, including projected expenditures plus anticipated liabilities.
Estimate Costs
Estimate Costs is the process of developing an approximate monetary assessment of the resources needed to complete project activities.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Determine Budget
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.