Estimate Costs
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Estimate Costs is the process of developing an approximate monetary assessment of the resources needed to complete project activities.
Know it well enough for the exam? Questions on Estimate Costs are scenario-based, not definitional.
Practice it freeExplanation
Estimate Costs involves developing a quantitative assessment of the probable costs of resources required to complete project work. Cost estimates are typically expressed in units of currency, though in some cases other units of measure such as staff hours or staff days may be used.
Costs are estimated for all resources charged to the project, including labor, materials, equipment, services, facilities, information technology, and special categories such as an inflation allowance, cost of financing, or contingency costs. The accuracy of a project estimate increases as the project progresses through its life cycle.
Key tools and techniques include analogous estimating, parametric estimating, bottom-up estimating, three-point estimating, data analysis (alternatives analysis and reserve analysis), the project management information system, and decision making. The primary outputs are activity cost estimates and the basis of estimates documentation.
Key Points
- •Estimates are refined as more information becomes available
- •Includes both direct and indirect costs
- •Activity cost estimates and basis of estimates are the key outputs
- •Uses multiple estimating techniques depending on available data
Exam Tip
Estimate Costs produces activity cost estimates, not the project budget. The budget is created in the Determine Budget process by aggregating cost estimates.
Frequently Asked Questions
Related Topics
Analogous Cost Estimating
Analogous cost estimating uses the cost of a previous, similar project or activity as the basis for estimating the cost of the current project or activity.
Parametric Cost Estimating
Parametric cost estimating uses a statistical relationship between historical data and other variables to calculate a cost estimate for project work.
Bottom-Up Cost Estimating
Bottom-up cost estimating involves estimating the cost of individual work packages or activities and then aggregating those estimates to arrive at a total project cost.
Three-Point Cost Estimating
Three-point cost estimating improves the accuracy of single-point estimates by considering estimation uncertainty and risk through optimistic, most likely, and pessimistic cost values.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Estimate Costs
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.