Cost Baseline
The cost baseline is the approved version of the time-phased project budget, excluding management reserves, used as a reference for measuring and monitoring cost performance.
Know it well enough for the exam? Questions on Cost Baseline are scenario-based, not definitional.
Practice it freeExplanation
The cost baseline is developed as a summation of the approved budgets for the different schedule activities. It is typically displayed in the form of an S-curve because project expenditures tend to start slowly, accelerate during execution, and then taper off during closing.
The cost baseline includes all authorized budgets, including contingency reserves for identified risks. It does not include management reserves. It is established through the Determine Budget process and can only be changed through the formal integrated change control process.
During project execution, the cost baseline serves as the benchmark against which actual costs are compared. Earned value management uses the cost baseline to calculate planned value and to measure cost and schedule performance. Any significant deviation from the cost baseline may trigger corrective actions or change requests.
Key Points
- •Approved, time-phased project budget excluding management reserves
- •Includes contingency reserves for identified risks
- •Displayed as an S-curve graph
- •Can only be changed through formal change control
Exam Tip
The cost baseline includes contingency reserves but NOT management reserves. It is the benchmark for EVM. Changes to the cost baseline require formal change control.
Frequently Asked Questions
Related Topics
Determine Budget
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Project Budget
The project budget is the total authorized funds allocated for the project, composed of the cost baseline plus management reserves.
S-Curve
An S-curve is a graphical display of cumulative costs, labor hours, or other quantities plotted against time, forming a characteristic S-shape.
Control Costs
Control Costs is the process of monitoring the status of the project to update project costs and managing changes to the cost baseline.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Cost Baseline
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.