Skip to content
PMPCAPM

Cost Baseline

The cost baseline is the approved version of the time-phased project budget, excluding management reserves, used as a reference for measuring and monitoring cost performance.

Share:

Explanation

The cost baseline is developed as a summation of the approved budgets for the different schedule activities. It is typically displayed in the form of an S-curve because project expenditures tend to start slowly, accelerate during execution, and then taper off during closing.

The cost baseline includes all authorized budgets, including contingency reserves for identified risks. It does not include management reserves. It is established through the Determine Budget process and can only be changed through the formal integrated change control process.

During project execution, the cost baseline serves as the benchmark against which actual costs are compared. Earned value management uses the cost baseline to calculate planned value and to measure cost and schedule performance. Any significant deviation from the cost baseline may trigger corrective actions or change requests.

Key Points

  • Approved, time-phased project budget excluding management reserves
  • Includes contingency reserves for identified risks
  • Displayed as an S-curve graph
  • Can only be changed through formal change control

Exam Tip

The cost baseline includes contingency reserves but NOT management reserves. It is the benchmark for EVM. Changes to the cost baseline require formal change control.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.