Skip to content
PMPCAPM

Funding Requirements

Funding requirements define the total and periodic funding needs derived from the cost baseline, including projected expenditures plus anticipated liabilities.

Share:

Know it well enough for the exam? Questions on Funding Requirements are scenario-based, not definitional.

Practice it free

Explanation

Funding requirements are an output of the Determine Budget process. They describe the total funds required as well as periodic (such as quarterly or annual) funding needs. Funding typically occurs in incremental amounts that are not continuous, appearing as a step function in graphical representation.

The total funds required are those described in the cost baseline plus management reserves. Funding requirements may include the source of the funding. The difference between funding and the cost baseline at any point in time is typically the management reserve.

Funding limit reconciliation may be necessary to adjust the expenditure of funds based on funding limitations. If a discrepancy exists between the funding limits and the planned expenditures, rescheduling of work may be required to level out the rate of expenditure. This is accomplished by imposing date constraints on work packages in the project schedule.

Key Points

  • •Output of the Determine Budget process
  • •Includes total and periodic funding needs
  • •Displayed as a step function on a graph
  • •May require funding limit reconciliation with scheduled work

Exam Tip

Funding requirements appear as a step function above the S-curve of the cost baseline. If funding does not match the planned expenditure rate, work may need to be rescheduled.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Funding Requirements

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.