Skip to content
PMPCAPM

Actual Cost (AC)

Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.

Explanation

Actual Cost, formerly known as Actual Cost of Work Performed (ACWP), represents the total costs actually incurred and recorded in accomplishing work during a given time period. AC includes all costs: labor, materials, equipment, overhead, and any other direct or indirect costs charged to the project.

AC has no upper limit in theory because overruns can exceed any planned amount. It is compared to EV to determine cost performance. If AC exceeds EV, the project is over budget for the work completed. If AC is less than EV, the project is under budget.

AC must be measured consistently with whatever was budgeted in PV and measured in EV. If PV includes only direct labor costs, then AC must also include only direct labor costs. This consistency is essential for meaningful EVM calculations.

Key Points

  • Formerly known as Actual Cost of Work Performed (ACWP)
  • Represents total costs incurred for completed work
  • Has no upper limit; can exceed planned amounts
  • Must be measured consistently with PV and EV for valid comparisons

Exam Tip

AC answers: What did the completed work actually cost? There is no upper limit for AC. Ensure AC is measured with the same cost elements as PV and EV.

Frequently Asked Questions

Related Topics

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.