Skip to content
PMPCAPM

Actual Cost (AC)

Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.

Share:

Explanation

Actual Cost, formerly known as Actual Cost of Work Performed (ACWP), represents the total costs actually incurred and recorded in accomplishing work during a given time period. AC includes all costs: labor, materials, equipment, overhead, and any other direct or indirect costs charged to the project.

AC has no upper limit in theory because overruns can exceed any planned amount. It is compared to EV to determine cost performance. If AC exceeds EV, the project is over budget for the work completed. If AC is less than EV, the project is under budget.

AC must be measured consistently with whatever was budgeted in PV and measured in EV. If PV includes only direct labor costs, then AC must also include only direct labor costs. This consistency is essential for meaningful EVM calculations.

Key Points

  • Formerly known as Actual Cost of Work Performed (ACWP)
  • Represents total costs incurred for completed work
  • Has no upper limit; can exceed planned amounts
  • Must be measured consistently with PV and EV for valid comparisons

Exam Tip

AC answers: What did the completed work actually cost? There is no upper limit for AC. Ensure AC is measured with the same cost elements as PV and EV.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.