Actual Cost (AC)
Actual Cost (AC) is the realized cost incurred for the work performed on an activity during a specific time period.
Know it well enough for the exam? Questions on Actual Cost (AC) are scenario-based, not definitional.
Practice it freeExplanation
Actual Cost, formerly known as Actual Cost of Work Performed (ACWP), represents the total costs actually incurred and recorded in accomplishing work during a given time period. AC includes all costs: labor, materials, equipment, overhead, and any other direct or indirect costs charged to the project.
AC has no upper limit in theory because overruns can exceed any planned amount. It is compared to EV to determine cost performance. If AC exceeds EV, the project is over budget for the work completed. If AC is less than EV, the project is under budget.
AC must be measured consistently with whatever was budgeted in PV and measured in EV. If PV includes only direct labor costs, then AC must also include only direct labor costs. This consistency is essential for meaningful EVM calculations.
Key Points
- •Formerly known as Actual Cost of Work Performed (ACWP)
- •Represents total costs incurred for completed work
- •Has no upper limit; can exceed planned amounts
- •Must be measured consistently with PV and EV for valid comparisons
Exam Tip
AC answers: What did the completed work actually cost? There is no upper limit for AC. Ensure AC is measured with the same cost elements as PV and EV.
Frequently Asked Questions
Related Topics
Earned Value (EV)
Earned Value (EV) is the measure of work performed expressed in terms of the budget authorized for that work.
Planned Value (PV)
Planned Value (PV) is the authorized budget assigned to scheduled work, representing the value of work planned to be completed by a given point in time.
Cost Variance (CV)
Cost Variance (CV) is an EVM metric that measures cost performance as the difference between earned value and actual cost: CV = EV - AC.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Actual Cost (AC)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.