Skip to content
PMPCAPM

S-Curve

An S-curve is a graphical display of cumulative costs, labor hours, or other quantities plotted against time, forming a characteristic S-shape.

Share:

Know it well enough for the exam? Questions on S-Curve are scenario-based, not definitional.

Practice it free

Explanation

The S-curve gets its name from the typical shape of cumulative project spending over time. Spending starts slowly during project initiation and planning, accelerates during execution as the majority of work is performed, and then tapers off during closing as the project winds down.

In earned value management, the S-curve is used to display the cost baseline (PV plotted over time), earned value (EV plotted over time), and actual cost (AC plotted over time) on the same graph. This visual representation makes it easy to identify schedule and cost variances at any point. The gap between the PV and EV curves shows schedule variance, while the gap between the EV and AC curves shows cost variance.

S-curves are also used for funding limit reconciliation, where the cumulative cost baseline is compared with funding step functions to ensure adequate funding is available at each stage of the project.

Key Points

  • •Shows cumulative costs or progress plotted against time
  • •Named for its characteristic S-shaped curve
  • •Used in EVM to display PV, EV, and AC simultaneously
  • •Visual gaps between curves reveal schedule and cost variances

Exam Tip

On an S-curve, the vertical gap between PV and EV at any point is SV, and the vertical gap between EV and AC is CV. Be able to read variances from an S-curve diagram.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice S-Curve

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.