Skip to content
PMPCAPM

Control Costs

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Control Costs is the process of monitoring the status of the project to update project costs and managing changes to the cost baseline.

Share:

Know it well enough for the exam? Questions on Control Costs are scenario-based, not definitional.

Start free

Explanation

Control Costs involves measuring actual cost performance against the cost baseline, analyzing variances, forecasting future cost performance, and taking corrective action when necessary. It is primarily concerned with ensuring that expenditures do not exceed the authorized funding and that cost changes are managed through integrated change control.

Key activities include monitoring cost expenditures against funds committed, preventing unapproved changes from being included in cost or resource usage reports, informing stakeholders of approved changes and associated costs, and bringing expected cost overruns within acceptable limits.

Earned value management (EVM) is a primary tool used in Control Costs. EVM integrates scope, schedule, and cost measures to assess project performance and progress. The process also produces work performance information, cost forecasts, change requests, and updates to the project management plan and project documents.

Key Points

  • •Monitors cost performance and manages changes to the cost baseline
  • •Uses earned value management as a primary tool
  • •Produces cost forecasts and work performance information
  • •Ensures changes go through integrated change control

Exam Tip

Control Costs is where EVM is applied. Know that this process compares actual costs to the cost baseline and produces forecasts like EAC and ETC.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Control Costs

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.