Skip to content
PMPCAPM

Workarounds

Workarounds are unplanned responses to risks that were not previously identified or to risks for which no planned response was adequate. They are developed in the moment when a risk event occurs without a contingency plan.

Share:

Know it well enough for the exam? Questions on Workarounds are scenario-based, not definitional.

Practice it free

Explanation

While contingency plans are preplanned responses for identified risks, workarounds are improvised responses created when an unidentified risk materializes or when a planned response proves insufficient. Workarounds are by nature reactive, developed under time pressure when the risk event has already occurred.

For example, if a server crashes due to an unforeseen hardware defect (a risk that was never identified), the team might create a workaround by quickly provisioning a cloud server as a temporary replacement. This was not planned in advance but addresses the immediate problem.

Workarounds should be documented in the risk register after they are implemented, along with the risk they addressed. They are reviewed during Monitor Risks to determine if additional follow-up is needed. Frequent reliance on workarounds may indicate that the Identify Risks process needs improvement, as it suggests many risks are being missed during planning.

Key Points

  • •Unplanned responses developed when unexpected risks materialize
  • •Reactive by nature, created under time pressure
  • •Documented in the risk register after implementation
  • •Frequent workarounds may signal inadequate risk identification

Exam Tip

Workaround = unplanned response to an unidentified risk. Contingency plan = preplanned response to an identified risk. The exam often tests this distinction.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Workarounds

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.