Skip to content
PMPCAPM

Identify Risks

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Identify Risks is the process of determining which risks may affect the project and documenting their characteristics. It is performed iteratively throughout the project.

Share:

Know it well enough for the exam? Questions on Identify Risks are scenario-based, not definitional.

Practice it free

Explanation

Identify Risks is a critical process that produces the initial entries in the risk register and contributes to the risk report. It involves systematically finding, recognizing, and describing risks that could have a positive or negative effect on one or more project objectives.

Common techniques include brainstorming, interviews, checklists, root cause analysis, SWOT analysis, assumption and constraint analysis, prompt lists, and document analysis. The Delphi technique (now called expert judgment with anonymity) can also be used to reduce bias. All project team members, stakeholders, and subject matter experts should be encouraged to participate.

This process is iterative because new risks emerge as the project progresses, deliverables are produced, and the environment changes. Each iteration may refine previously identified risks or uncover entirely new ones. The goal is to build a comprehensive, living inventory of risks rather than a one-time list.

Key Points

  • •Iterative process performed throughout the project lifecycle
  • •Uses brainstorming, interviews, checklists, SWOT, and root cause analysis
  • •Produces initial risk register entries and updates the risk report
  • •All stakeholders and team members should participate in identification

Exam Tip

Identify Risks is the only risk process that is explicitly iterative by definition in the PMBOK. Expect questions about when and how often to revisit risk identification.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Identify Risks

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.