Monitor Risks
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.
Know it well enough for the exam? Questions on Monitor Risks are scenario-based, not definitional.
Practice it freeExplanation
Monitor Risks is a continuous process performed throughout the project. It involves tracking the status of identified risks, checking whether risk triggers have occurred, evaluating the effectiveness of implemented responses, identifying new risks that emerge, and ensuring the risk management plan is being followed.
Key activities include risk reassessments (periodic reviews of the entire risk register), risk audits (evaluating the effectiveness of the risk management process itself), variance and trend analysis (comparing actual results to expected baselines), and monitoring reserve status (checking whether contingency reserves are adequate).
The process produces work performance information about risk status, change requests when new responses are needed or baselines must be adjusted, and updates to project documents including the risk register, risk report, assumption log, issue log, and lessons learned register. Effective risk monitoring ensures that the project stays proactive rather than reactive.
Key Points
- •Continuous process throughout the project lifecycle
- •Includes risk reassessments, audits, and reserve analysis
- •Tracks triggers, evaluates response effectiveness, identifies new risks
- •Outputs include change requests and updated project documents
Exam Tip
Risk audits evaluate the effectiveness of the risk management process, not individual risks. Risk reassessments re-examine individual risks. Know the difference.
Frequently Asked Questions
Related Topics
Implement Risk Responses
Implement Risk Responses is the process of executing the agreed-upon risk response plans. It ensures that risk responses are carried out as planned, with the goal of minimizing threats and maximizing opportunities.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Risk Triggers
Risk triggers (also called risk symptoms or warning signs) are events or conditions that indicate a risk is about to occur or has already occurred. They signal the need to activate a risk response.
Workarounds
Workarounds are unplanned responses to risks that were not previously identified or to risks for which no planned response was adequate. They are developed in the moment when a risk event occurs without a contingency plan.
Secondary Risks and Residual Risks
Secondary risks are new risks that arise as a direct result of implementing a risk response. Residual risks are risks that remain after planned responses have been implemented, including minor risks that were deliberately accepted.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Monitor Risks
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.