Accept (Risk Strategy)
Accept is a risk response strategy where the project team acknowledges a risk but takes no proactive action to address it. Acceptance can be passive (do nothing) or active (establish a contingency reserve or plan).
Know it well enough for the exam? Questions on Accept (Risk Strategy) are scenario-based, not definitional.
Practice it freeExplanation
Risk acceptance is appropriate when the risk has low probability or impact, when no cost-effective response is available, or when the risk cannot be addressed through other strategies. It is used for both threats and opportunities.
Passive acceptance requires no action other than documenting the risk and reviewing it periodically. The team deals with the risk if and when it occurs. Active acceptance involves establishing a contingency reserve (time or money) or developing a contingency plan that is triggered only if the risk event occurs.
For example, a team might passively accept the risk of minor weather delays on an outdoor event. For a more significant risk, they might actively accept by setting aside a contingency budget of $20,000 to cover potential weather-related costs. The contingency plan provides a predefined response without proactively preventing the risk.
Key Points
- •Acknowledges risk without proactive prevention
- •Passive acceptance: no action taken, deal with it if it occurs
- •Active acceptance: contingency reserve or contingency plan established
- •Appropriate for low-priority risks or when no cost-effective response exists
Exam Tip
Know the difference between active and passive acceptance. Active acceptance establishes a contingency reserve or plan; passive acceptance has no preplanned response.
Frequently Asked Questions
Related Topics
Risk Response Strategies for Threats
Risk response strategies for threats are the five approaches available to address negative risks: avoid, mitigate, transfer, accept, and escalate. Each strategy aims to reduce the probability, impact, or exposure of a threat.
Risk Response Strategies for Opportunities
Risk response strategies for opportunities are the five approaches used to address positive risks: exploit, enhance, share, accept, and escalate. Each strategy aims to increase the probability, impact, or both of a beneficial risk event.
Plan Risk Responses
Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure and to treat individual project risks.
Workarounds
Workarounds are unplanned responses to risks that were not previously identified or to risks for which no planned response was adequate. They are developed in the moment when a risk event occurs without a contingency plan.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Accept (Risk Strategy)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.