Skip to content
PMPCAPM

Work Performance Data

Work performance data is the raw observations and measurements identified during activities performed to carry out the project work.

Share:

Know it well enough for the exam? Questions on Work Performance Data are scenario-based, not definitional.

Practice it free

Explanation

Work performance data is the first level in a three-tier hierarchy of project performance information. It consists of the raw, unprocessed facts and figures gathered during project execution. Examples include actual start and finish dates of activities, number of change requests, number of defects, actual costs incurred, actual durations, percent of work physically completed, and technical performance measurements.

This data by itself has limited meaning — it is simply raw numbers and observations. Its value emerges when it is analyzed in the Monitoring and Controlling processes and compared against the project management plan to produce work performance information. For example, knowing that a task took 12 days (work performance data) only becomes meaningful when compared against the planned 10 days (producing a variance of 2 days, which is work performance information).

Work performance data is generated in the Executing Process Group, specifically from the Direct and Manage Project Work process. From there, it flows into various controlling processes — Control Schedule, Control Costs, Control Quality, and others — where it is analyzed and contextualized.

Key Points

  • •Raw observations and measurements from project execution
  • •First level in the data-information-reports hierarchy
  • •Includes actual dates, costs, durations, and defect counts
  • •Generated during execution, analyzed during monitoring and controlling

Exam Tip

Remember the hierarchy: Data (raw) -> Information (analyzed) -> Reports (formatted for communication). If the exam describes raw measurements with no analysis, it is work performance data.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Predictive Life Cycle (Waterfall)

A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.

Subsidiary Plans

Subsidiary plans are the individual management plans that are components of the overall project management plan, each addressing a specific Knowledge Area or management function.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

PM Fundamentals & Frameworks

Study full domain →

Practice Work Performance Data

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.