Skip to content
PMPCAPM

Subsidiary Plans

Subsidiary plans are the individual management plans that are components of the overall project management plan, each addressing a specific Knowledge Area or management function.

Share:

Know it well enough for the exam? Questions on Subsidiary Plans are scenario-based, not definitional.

Practice it free

Explanation

The project management plan is composed of multiple subsidiary plans, each focused on a specific aspect of project management. The standard subsidiary plans include the scope management plan, requirements management plan, schedule management plan, cost management plan, quality management plan, resource management plan, communications management plan, risk management plan, procurement management plan, and stakeholder engagement plan.

Each subsidiary plan defines the approach, processes, and procedures for managing its respective area. For example, the risk management plan describes how risks will be identified, analyzed, prioritized, and responded to. The communications management plan defines who needs what information, when, in what format, and through what channels. The cost management plan establishes the units of measure, level of precision, control thresholds, and earned value rules.

Subsidiary plans are developed during the Planning Process Group and become components of the integrated project management plan. They do not exist in isolation — they work together and must be consistent with each other. Changes to one subsidiary plan often have implications for others, which is why integrated change control is so important.

Key Points

  • •Individual management plans for each Knowledge Area or function
  • •Components of the overall project management plan
  • •Include scope, schedule, cost, quality, resource, communications, risk, procurement, and stakeholder plans
  • •Must be consistent with each other and integrated through the master plan

Exam Tip

Know what each subsidiary plan defines. The exam may present a scenario and ask which plan governs the described activity. For example, "how will stakeholder information needs be addressed?" points to the communications management plan.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Predictive Life Cycle (Waterfall)

A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

PM Fundamentals & Frameworks

Study full domain →

Practice Subsidiary Plans

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.