Skip to content
PMPCAPM

Secondary Risks and Residual Risks

Secondary risks are new risks that arise as a direct result of implementing a risk response. Residual risks are risks that remain after planned responses have been implemented, including minor risks that were deliberately accepted.

Share:

Know it well enough for the exam? Questions on Secondary Risks and Residual Risks are scenario-based, not definitional.

Practice it free

Explanation

When a risk response is executed, it may inadvertently create new risks. These new risks, called secondary risks, must be identified, analyzed, and managed just like any primary risk. For example, if the team transfers a risk by outsourcing a component to a vendor, a secondary risk might emerge: the vendor may not meet quality standards. This secondary risk needs its own response strategy.

Residual risks are the risks that persist after all planned responses have been applied. No risk response eliminates all exposure entirely (except avoidance, which eliminates the specific risk). Mitigation reduces probability or impact, but some level of risk remains. This residual risk should be documented, communicated to stakeholders, and may require contingency reserves.

Both secondary and residual risks must be recorded in the risk register and monitored throughout the project. They should go through the same qualitative and quantitative analysis processes as primary risks. Failure to account for secondary and residual risks can lead to underestimating the project's true risk exposure.

Key Points

  • •Secondary risks arise from implementing a risk response
  • •Residual risks remain after planned responses are executed
  • •Both must be documented in the risk register and managed like primary risks
  • •Contingency reserves may be needed for accepted residual risks

Exam Tip

A classic exam question: "A new risk emerged after implementing a response." This is a secondary risk. Know the difference between secondary (caused by the response) and residual (remaining after the response).

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Secondary Risks and Residual Risks

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.