Mitigate (Risk Strategy)
Mitigate is a threat response strategy that reduces the probability of occurrence and/or the impact of a threat to within acceptable limits. The risk is not eliminated but brought to a manageable level.
Know it well enough for the exam? Questions on Mitigate (Risk Strategy) are scenario-based, not definitional.
Practice it freeExplanation
Mitigation involves taking early action to decrease either the likelihood that a threat will materialize or the severity of its consequences if it does. Common mitigation techniques include adding testing or reviews, selecting more experienced resources, adopting proven methodologies, building prototypes, adding redundancy, and simplifying processes.
For example, if there is a risk of a critical system component not passing a performance test, mitigation might include conducting early performance benchmarks, engaging specialized engineers, or adding a parallel testing track. These actions do not eliminate the risk of test not passing, but they significantly reduce its probability.
Mitigation is the most commonly used threat response strategy because it is often more practical than avoidance and more proactive than acceptance. However, the cost of mitigation actions must be weighed against the expected reduction in risk exposure. Residual risk (the risk remaining after mitigation) should be documented in the risk register.
Key Points
- •Reduces probability or impact of a threat to acceptable levels
- •Does not eliminate the risk; residual risk remains
- •Examples: prototyping, testing, training, redundancy, proven methods
- •Most commonly used threat response strategy
Exam Tip
Mitigation reduces the risk but does not eliminate it. After mitigation, the remaining risk is called residual risk and must be documented.
Frequently Asked Questions
Related Topics
Risk Response Strategies for Threats
Risk response strategies for threats are the five approaches available to address negative risks: avoid, mitigate, transfer, accept, and escalate. Each strategy aims to reduce the probability, impact, or exposure of a threat.
Avoid (Risk Strategy)
Avoid is a threat response strategy that eliminates the threat by changing the project management plan to remove the risk entirely, protect the project objectives, or relax the objective that is at risk.
Secondary Risks and Residual Risks
Secondary risks are new risks that arise as a direct result of implementing a risk response. Residual risks are risks that remain after planned responses have been implemented, including minor risks that were deliberately accepted.
Plan Risk Responses
Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure and to treat individual project risks.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Mitigate (Risk Strategy)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.