Skip to content
PMPCAPM

Plan Risk Responses

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure and to treat individual project risks.

Share:

Know it well enough for the exam? Questions on Plan Risk Responses are scenario-based, not definitional.

Practice it free

Explanation

Plan Risk Responses takes prioritized risks from the risk register and determines the most appropriate response strategy for each. For threats, the strategies are avoid, mitigate, transfer, accept, and escalate. For opportunities, the strategies are exploit, enhance, share, accept, and escalate.

Effective risk responses must be appropriate to the severity of the risk, cost-effective relative to the risk exposure, realistic within the project context, agreed upon by relevant stakeholders, owned by a responsible person (risk owner), and timely. The response should reduce the overall threat exposure or increase the opportunity exposure.

The process also addresses overall project risk through strategies such as restructuring the project, adjusting scope or schedule, or communicating the overall risk position to stakeholders. Outputs include updates to the risk register (with response strategies, owners, triggers, contingency and fallback plans), updates to the project management plan, and change requests when responses require changes to baselines.

Key Points

  • •Selects strategies for threats (avoid, mitigate, transfer, accept, escalate) and opportunities (exploit, enhance, share, accept, escalate)
  • •Each risk response must have an assigned risk owner
  • •Responses must be cost-effective, timely, and agreed upon by stakeholders
  • •May generate change requests when responses affect baselines

Exam Tip

Every risk response needs a risk owner. On the exam, if a question asks what is missing from a risk response, check whether an owner has been assigned.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Plan Risk Responses

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.