Plan Risk Responses
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure and to treat individual project risks.
Know it well enough for the exam? Questions on Plan Risk Responses are scenario-based, not definitional.
Practice it freeExplanation
Plan Risk Responses takes prioritized risks from the risk register and determines the most appropriate response strategy for each. For threats, the strategies are avoid, mitigate, transfer, accept, and escalate. For opportunities, the strategies are exploit, enhance, share, accept, and escalate.
Effective risk responses must be appropriate to the severity of the risk, cost-effective relative to the risk exposure, realistic within the project context, agreed upon by relevant stakeholders, owned by a responsible person (risk owner), and timely. The response should reduce the overall threat exposure or increase the opportunity exposure.
The process also addresses overall project risk through strategies such as restructuring the project, adjusting scope or schedule, or communicating the overall risk position to stakeholders. Outputs include updates to the risk register (with response strategies, owners, triggers, contingency and fallback plans), updates to the project management plan, and change requests when responses require changes to baselines.
Key Points
- •Selects strategies for threats (avoid, mitigate, transfer, accept, escalate) and opportunities (exploit, enhance, share, accept, escalate)
- •Each risk response must have an assigned risk owner
- •Responses must be cost-effective, timely, and agreed upon by stakeholders
- •May generate change requests when responses affect baselines
Exam Tip
Every risk response needs a risk owner. On the exam, if a question asks what is missing from a risk response, check whether an owner has been assigned.
Frequently Asked Questions
Related Topics
Risk Response Strategies for Threats
Risk response strategies for threats are the five approaches available to address negative risks: avoid, mitigate, transfer, accept, and escalate. Each strategy aims to reduce the probability, impact, or exposure of a threat.
Risk Response Strategies for Opportunities
Risk response strategies for opportunities are the five approaches used to address positive risks: exploit, enhance, share, accept, and escalate. Each strategy aims to increase the probability, impact, or both of a beneficial risk event.
Implement Risk Responses
Implement Risk Responses is the process of executing the agreed-upon risk response plans. It ensures that risk responses are carried out as planned, with the goal of minimizing threats and maximizing opportunities.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Plan Risk Responses
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.