Skip to content
PMPCAPM

Reserve Analysis

Reserve analysis is a technique used to determine the amount of contingency and management reserves needed for a project to account for cost uncertainty and risk.

Share:

Know it well enough for the exam? Questions on Reserve Analysis are scenario-based, not definitional.

Practice it free

Explanation

Reserve analysis is an analytical technique used to establish both contingency reserves and management reserves for a project. It addresses the question of how much reserve is appropriate given the level of uncertainty and risk in the project.

Contingency reserves are budget amounts set aside for identified risks that are accepted and for which contingent responses are developed. Management reserves are budget amounts held for unplanned changes to project scope and cost that management controls. Together, these reserves help ensure that the project can absorb cost overruns without failing.

Reserve analysis can use various approaches, including percentage of estimated cost, fixed number, or quantitative risk analysis methods such as Monte Carlo simulation. As the project progresses and more information becomes available, reserves may be used, reduced, or eliminated. Any remaining contingency reserve can be released when the associated risk is no longer active.

Key Points

  • •Determines both contingency and management reserve amounts
  • •Can use percentage, fixed number, or simulation techniques
  • •Reserves are reviewed and adjusted throughout the project
  • •Unused reserves may be released as risks are retired

Exam Tip

Reserve analysis is a technique, not a reserve itself. It produces the reserve amounts. Know the difference between contingency reserves (for known risks) and management reserves (for unknown risks).

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Reserve Analysis

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.