Skip to content
PMPCAPM

Contingency Reserves

Contingency reserves are budget amounts allocated within the cost baseline to address identified risks that have been accepted and for which contingent or mitigating responses have been developed.

Share:

Explanation

Contingency reserves are funds set aside to handle identified risks, also referred to as "known unknowns." These reserves are included in the cost baseline and are under the control of the project manager. They represent an estimated amount needed to address specific risks if they occur.

Contingency reserves can be estimated using various methods, including a percentage of the estimated activity cost, a fixed amount, or through quantitative analysis techniques. As the project progresses and identified risks either occur or are retired, the contingency reserves are adjusted accordingly.

The project manager has the authority to use contingency reserves without requiring a change request because they are part of the cost baseline. However, the project manager must document the use of these reserves and report on the remaining balance. This is different from management reserves, which require a change request for use.

Key Points

  • Allocated for identified risks (known unknowns)
  • Included within the cost baseline
  • Managed by the project manager without change requests
  • Adjusted as risks are resolved or retired throughout the project

Exam Tip

Contingency reserves are part of the cost baseline and are controlled by the project manager. They address known unknowns. No change request is needed to use them.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.