Skip to content
PMPCAPM

Contingency Reserves

Contingency reserves are budget amounts allocated within the cost baseline to address identified risks that have been accepted and for which contingent or mitigating responses have been developed.

Share:

Know it well enough for the exam? Questions on Contingency Reserves are scenario-based, not definitional.

Practice it free

Explanation

Contingency reserves are funds set aside to handle identified risks, also referred to as "known unknowns." These reserves are included in the cost baseline and are under the control of the project manager. They represent an estimated amount needed to address specific risks if they occur.

Contingency reserves can be estimated using various methods, including a percentage of the estimated activity cost, a fixed amount, or through quantitative analysis techniques. As the project progresses and identified risks either occur or are retired, the contingency reserves are adjusted accordingly.

The project manager has the authority to use contingency reserves without requiring a change request because they are part of the cost baseline. However, the project manager must document the use of these reserves and report on the remaining balance. This is different from management reserves, which require a change request for use.

Key Points

  • •Allocated for identified risks (known unknowns)
  • •Included within the cost baseline
  • •Managed by the project manager without change requests
  • •Adjusted as risks are resolved or retired throughout the project

Exam Tip

Contingency reserves are part of the cost baseline and are controlled by the project manager. They address known unknowns. No change request is needed to use them.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Contingency Reserves

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.