Skip to content
PMPCAPM

Management Reserves

Management reserves are budget amounts set aside for unforeseen work within the scope of the project, intended to address unknown risks that cannot be predicted during planning.

Share:

Know it well enough for the exam? Questions on Management Reserves are scenario-based, not definitional.

Practice it free

Explanation

Management reserves are an amount of the project budget withheld for management control purposes. They are reserved for unknown unknowns, which are risks that cannot be anticipated or planned for. These reserves are not included in the cost baseline but are part of the overall project budget.

Because management reserves are outside the cost baseline, using them requires a change request approved by the appropriate level of management. When management reserves are used, the funds are added to the cost baseline, effectively updating it through the integrated change control process.

Management reserves are typically expressed as a percentage of the total project cost, often ranging from 5% to 10% depending on the organization and project uncertainty. They provide a buffer for truly unexpected events that fall within the general scope of the project but were not specifically identified during risk planning.

Key Points

  • •Allocated for unknown risks (unknown unknowns)
  • •Not included in the cost baseline but part of the project budget
  • •Require a change request and management approval to use
  • •Typically expressed as a percentage of total project cost

Exam Tip

Management reserves are NOT part of the cost baseline. They require a change request to use. This is the key difference from contingency reserves, which are within the baseline.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Cost Management

Study full domain →

Practice Management Reserves

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.