Skip to content
PMPCAPM

RACI Matrix

A RACI matrix is a type of responsibility assignment matrix that defines roles as Responsible, Accountable, Consulted, or Informed for each work package or activity.

Share:

Know it well enough for the exam? Questions on RACI Matrix are scenario-based, not definitional.

Practice it free

Explanation

The RACI matrix is one of the most commonly used formats of the responsibility assignment matrix (RAM). For each task or deliverable, it assigns exactly one person who is Accountable (the decision-maker who approves the work), one or more people who are Responsible (those who do the work), people who are Consulted (who provide input before the work is done), and people who are Informed (who are kept updated on progress or decisions).\n\nA key rule is that there should be exactly one Accountable person for each task. Having more than one Accountable person creates confusion about who has final authority. There can be multiple Responsible, Consulted, and Informed parties. The matrix is typically presented in a grid with tasks on the rows and team members or roles on the columns.\n\nThe RACI matrix is developed during the Plan Resource Management process and helps clarify roles and responsibilities, reduce ambiguity, and ensure that no tasks fall through the cracks. It is particularly useful on cross-functional projects where team members report to different functional managers.

Key Points

  • •R = Responsible (does the work), A = Accountable (approves/owns), C = Consulted (provides input), I = Informed (kept updated)
  • •Exactly one Accountable person per task is required
  • •Multiple Responsible, Consulted, and Informed parties are allowed
  • •Developed during Plan Resource Management

Exam Tip

On the exam, if a question mentions confusion about who is making decisions, the answer often involves creating or updating the RACI matrix. Remember: only one A per task.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Resource Management

Study full domain →

Practice RACI Matrix

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.