Skip to content
PMPCAPM

Manage Team

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Manage Team is the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance.

Share:

Know it well enough for the exam? Questions on Manage Team are scenario-based, not definitional.

Practice it free

Explanation

Manage Team involves observing team behavior, managing conflict, resolving issues, and appraising team member performance. This process requires a combination of management and leadership skills, including communication, conflict management, negotiation, and influencing. The project manager must be sensitive to both the willingness and ability of team members to perform their work.\n\nKey tools and techniques include interpersonal and team skills (conflict management, decision-making, emotional intelligence, influencing, and leadership) and the project management information system. The project manager relies on observation and conversation to stay in touch with the work and attitudes of team members.\n\nOutputs include change requests and updates to the project management plan, project documents (such as the issue log, lessons learned register, and project team assignments), and enterprise environmental factors. This process is performed throughout the project and is part of the Executing process group.

Key Points

  • •Tracks performance and provides feedback to team members
  • •Resolves conflicts and manages team changes
  • •Part of the Executing process group
  • •Relies heavily on interpersonal skills including emotional intelligence

Exam Tip

Manage Team is in the Executing process group, not Monitoring & Controlling. Conflict resolution, performance appraisals, and issue resolution happen here.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Resource Management

Study full domain →

Practice Manage Team

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.