Analogous Cost Estimating
Analogous cost estimating uses the cost of a previous, similar project or activity as the basis for estimating the cost of the current project or activity.
Know it well enough for the exam? Questions on Analogous Cost Estimating are scenario-based, not definitional.
Practice it freeExplanation
Analogous estimating, also called top-down estimating, relies on historical data from similar projects to produce cost estimates. It uses parameters such as scope, cost, budget, duration, and complexity from a previous project as the basis for estimating the same parameters for the current project.
This technique is most reliable when previous projects are similar in fact and not just in appearance, and when the individuals preparing the estimates have the needed expertise. It is typically used when there is limited information about the current project, such as in the early phases.
Analogous estimating is generally less costly and less time-consuming than other techniques but is also less accurate. It can be applied to an entire project or to segments of a project and may be used in combination with other estimating methods.
Key Points
- •Also known as top-down estimating
- •Uses historical data from similar projects
- •Less costly and time-consuming but less accurate
- •Best used in early project phases when detail is limited
Exam Tip
Analogous estimating is quick and inexpensive but least accurate. It relies on expert judgment and historical similarity. Think "top-down" when you see analogous.
Frequently Asked Questions
Related Topics
Parametric Cost Estimating
Parametric cost estimating uses a statistical relationship between historical data and other variables to calculate a cost estimate for project work.
Bottom-Up Cost Estimating
Bottom-up cost estimating involves estimating the cost of individual work packages or activities and then aggregating those estimates to arrive at a total project cost.
Estimate Costs
Estimate Costs is the process of developing an approximate monetary assessment of the resources needed to complete project activities.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Analogous Cost Estimating
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.