Parametric Cost Estimating
Parametric cost estimating uses a statistical relationship between historical data and other variables to calculate a cost estimate for project work.
Know it well enough for the exam? Questions on Parametric Cost Estimating are scenario-based, not definitional.
Practice it freeExplanation
Parametric estimating uses an algorithm or mathematical model to estimate costs based on historical data and project parameters. For example, if historical data shows that a square foot of construction costs $200, and the project requires 10,000 square feet, the parametric estimate would be $2,000,000.
The accuracy of parametric estimates depends on the sophistication and reliability of the underlying model and the data used. This technique can be applied to an entire project or to parts of a project, and it can be used in conjunction with other estimating methods.
Parametric estimating can produce higher levels of accuracy than analogous estimating depending on the maturity of the model and the data. It is most reliable when the historical data used to develop the model is accurate, the parameters used in the model are readily quantifiable, and the model is scalable.
Key Points
- •Uses statistical relationships and mathematical models
- •Accuracy depends on the quality of the underlying model and data
- •Can be highly accurate when the model is mature and data is reliable
- •Scalable across different project sizes
Exam Tip
Parametric estimating uses a unit rate multiplied by quantity (e.g., cost per line of code multiplied by number of lines). It is more accurate than analogous when the model is sound.
Frequently Asked Questions
Related Topics
Analogous Cost Estimating
Analogous cost estimating uses the cost of a previous, similar project or activity as the basis for estimating the cost of the current project or activity.
Bottom-Up Cost Estimating
Bottom-up cost estimating involves estimating the cost of individual work packages or activities and then aggregating those estimates to arrive at a total project cost.
Estimate Costs
Estimate Costs is the process of developing an approximate monetary assessment of the resources needed to complete project activities.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Parametric Cost Estimating
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.